LAND
For spatial planning, the Dutch government applies zoning plans. At Agriport, the zoning plan has been established for the establishment of datacenters on an area of 175 acres.
An environmental survey has already been conducted. An additional environmental permit is therefore not necessary.
The land is flat and has accessibility by public roads, less than 3 miles from the A7 motorway exit.
The underground is soft (clay, sand). Before construction, a ground survey needs to be conducted to establish the length of the piling for the construction.